Project Schedule

Final selection and adoption of preferred alignment alternative
(January - February 2007)

Begin Final Design
(March 2007)

  • Contact and meet individually with owners of impacted properties.

Begin Property Acquisition for Roadway Project
(April 2007)

  • Most properties will be appraised between June 2007 and February of 2008.
  • Properties requiring relocation services (full acquisition properties) will be the first group of properties appraised.

Project Design Complete
(August 2008)

Construction
(January 2009 - December 2010)

  • 172nd Ave will be closed to through traffic during construction. Road will be open to local and emergency vehicles only

 

click to enlarge

   
click to enlarge

 

click to enlarge

 

click to enlarge

 

click to enlarge

 

click to enlarge

 

click to enlarge
     
This site was created by Harper Houf Peterson Righellis Inc. Copyright © 2009 | hhpr.com  
Clackamas County Website