Project Schedule
Final selection and adoption of preferred alignment alternative
(January - February 2007)
Begin Final Design
(March 2007)
- Contact and meet individually with owners of impacted properties.
Begin Property Acquisition for Roadway Project
(April 2007)
- Most properties will be appraised between June 2007 and February of 2008.
- Properties requiring relocation services (full acquisition properties) will be the first group of properties appraised.
Project Design Complete
(August 2008)
Construction
(January 2009 - December 2010)
- 172nd Ave will be closed to through traffic during construction. Road will be open to local and emergency vehicles only

|