Project Overview

In the 1990s, community members and Clackamas County began working on solutions to the ever-increasing traffic congestion along Sunnyside Road between I-205 and 172nd Avenue. At the time, Sunnyside Road was an overburdened rural two-lane roadway. Today, pedestrians, cyclists and motorists can travel safely and conveniently from I-205 to SE 162nd Avenue. The last phase, Phase 3B (162nd and 172nd) is anticipated to be completed by 2008. Plans for extension beyond 172nd Avenue to the east are currently being explored by the City of Damascus.


Phase 1
Phase 2 & 3A
Phase 3B
Completed in 2004
Completed in 2006
Under Construction now!